This project consists of the installation of an interceptor sewer with a pipe size of 36 inch at varying depth up to 35 feet. It will also eliminate two lift stations and replace them with gravity sewer. This sewer connects to an existing 42 inch sewer and runs East, crosses under a CSX rail, turns South and crosses under Honey Creek, and terminates in Woodgate Subdivision.  
 
Project Began:                       September 10, 2007
Substantial Completion:        September 10, 2008
Final Completion:                   May 1, 2009
Construction Cost:                 $2,200,000.00
Funding Source:                     Sanitary District Project 22
 